Current Condition – Tuesday November 10, 2026
Condition
General Traffic Status
Public Vehicle Access
B
Open During Commute Periods / Closed Midday
Open: 12:01 a.m.-9:00 a.m. &
3:00 p.m.-12:00 p.m.
Closed: 9:00 a.m.-3:00 p.m.
During the midday closure, resident vehicle crossings are not guaranteed. A request must be submitted at least 24 hours in advance and any crossing remains subject to approval by the Site Superintendent. Residents may park a vehicle south of the bridge and return it home during the evening open period.
Special Notes
The Tuesday and Wednesday work schedule involves the removal of the old ramps and fitting the modular ramps.
- The road closure will not be able to accommodate crossings during the closed period.
- Special accommodations have been put in place for Emergency Services and Garbage Collection. These vehicles will be permitted through the site.
Site conditions and access may change. Sign boards located on site will be the most up to date reference and may allow for additional crossing opportunities.
Upcoming Condition – December 7, 2026 until: up to December 14, 2026
Condition
General Traffic Status
Public Vehicle Access
C
Full Road Closure
The road is fully closed to public vehicles. No public vehicle crossing is available. Residents may leave a vehicle south of the bridge before the closure. Shuttle arrangements for the north side will be confirmed in a separate notice before the closure begins.
Special Notes
- Continuous pedestrian access will be maintained for emergency services. The Municipality is arranging for emergency vehicles staged on the far side in case of an emergency along the road
- Pedestrian access will be permitted for residents during this time. Resident access may be temporarily be restricted based on construction operations occuring at the time. Follow instructions on the sign boards to ensure safe crossing protocols are followed.
- Additional details are available in the notice.
November 20, 2025
Notice: Road Closure Starting December 7th, 2026
As part of the Leeftink Road Bridge Replacement, a full road closure at the bridge site will be required to facilitate the safe removal and replacement of the existing structure. The closure is scheduled to occur from December 7, 2026, to December 14, 2026.
Continuous pedestrian access across the bridge will be maintained for first responders in the event of an emergency. The Municipality will arrange for emergency service vehicles to be stationed on the isolated side of the bridge. In the event of an emergency, first responders will cross the bridge on foot and continue using the emergency service vehicles positioned on the opposite side.
During the closure, pedestrian access will also be permitted for residents to travel between their homes on the north side of the bridge and their vehicles parked within the designated control zone on the south side of the bridge. This access will be maintained for the duration of the closure; however, passage may be temporarily restricted during active construction operations and will be permitted only when site conditions allow for safe pedestrian movement.
Residents are asked to follow all posted signage and directions provided by site personnel to ensure the safety of both the public and construction workers.
Notice: Traffic Restriction Starting November 10, 2026
November 6, 2026
Please note that traffic restrictions will be entering condition B as of November 10, 2026. The road will be closed between the hours of 9am and 3pm on weekdays to accommodate work in the roadway. The road will be open to normal traffic daily from 3pm to 9am and on weekends. Access may be scheduled ahead of time by contacting the team through approved channels listed in the Bridge Crossing Protocol and is not guaranteed. On site sign boards will be in place to provide the most current status of the site and access instructions. A few special notes regarding this closure:
- The road closure will not be able to accommodate crossings during the closed period.
- Special accommodations have been put in place for Emergency Services and Garbage Collection. These vehicles will be permitted through the site.
Condition
General Traffic Status
Public Vehicle Access
A
Road Open
The road remains open. Traffic control persons may stop vehicles periodically for up to 15 minutes
Condition
General Traffic Status
Public Vehicle Access
B
Open During Commute Periods / Closed Midday
Open: 12:01 a.m.-9:00 a.m. &
3:00 p.m.-12:00 p.m.
Closed: 9:00 a.m.-3:00 p.m.
During the midday closure, resident vehicle crossings are not guaranteed. A request must be submitted at least 24 hours in advance and any crossing remains subject to approval by the Site Superintendent. Residents may park a vehicle south of the bridge and return it home during the evening open period.
Condition
General Traffic Status
Public Vehicle Access
C
Full Road Closure
The road is fully closed to public vehicles. No public vehicle crossing is available. Residents may leave a vehicle south of the bridge before the closure. Shuttle arrangements for the north side will be confirmed in a separate notice before the closure begins.
Current Condition
November 9, 2026 – December 6, 2026
December 7, 2026 – December 11, 2026
December 12 2026
| BRIDGE ACCESS DURING CONSTRUCTION Instructions for residents LEEFTINK RD BRIDGE REPLACEMENT | LEEFTINK ROAD | EFFECTIVE 2026-10-26 TO 2026-12-18 |
| THE ROAD WILL GENERALLY BE CLOSED WITH THE EXCEPTION OF MORNING AND EVENING COMMUTE PERIODS BELOW: 6:00 AM AND 9:00 AM AND BETWEEN 3:00 PM AND 6:00 PM, MONDAY TO FRIDAY, AND AT ALL TIMES ON WEEKENDS. Construction equipment must stop and the route must be made safe before you cross. Morning and evening access periods will be provided as stated in the Contract. Additional crossing requests will be considered when field conditions allow. |
| REQUEST ACCESS Call or text (705) 690-7007 | EMERGENCY Call 911 first | CURRENT UPDATES Check the notice board at either bridge approach |
HOW TO REQUEST AN ADDITIONAL CROSSING
| 1 | CALL OR TEXT THE PROJECT ACCESS NUMBER Contact [PROJECT ACCESS NUMBER] at least [60 minutes] before your preferred crossing time. Requests are best efforts and may be delayed by active construction. |
| 2 | PROVIDE THE KEY DETAILS Give your name, callback number, preferred time, direction of travel, vehicle or pedestrian access, flexibility, and any accessibility need that affects the crossing. |
| 3 | WAIT FOR A STATUS MESSAGE The RVA Site Inspector will provide one status: ACCEPTED with a proposed time, PENDING with the next update time, or DECLINED with the reason and next available opportunity. |
| 4 | CONFIRM YOUR PROPOSED TIME Reply “CONFIRMED [Request ID]” by the stated deadline. If you do not reply, the Inspector will call once. Until confirmation is received, your request remains pending and the time may be released. |
| 5 | ARRIVE AT THE HOLDING POINT Arrive approximately [5 minutes] early and stop at the signed holding point. Do not drive toward the bridge. If you are late, the crossing opportunity may have to be rescheduled. |
| 6 | WAIT FOR THE TRAFFIC CONTROLLER A confirmed time reserves an opportunity only. Proceed only after the Contractor has made the route safe and the traffic controller gives you a clear signal. |
CHECK THE NOTICEBOARD BEFORE EVERY TRIP
| i | WHERE TO FIND IT A notice board will be located at the designated holding point on each side of the bridge. Stop where it is safe and remain outside the work zone. |
| ↻ | WHAT TO CHECK Confirm the active project access number, normal access periods, holding-point location, schedule changes, current restrictions, and the date and time of the latest update. |
| ! | IF THE INFORMATION HAS CHANGED Follow the newest dated notice and any direct instruction from the RVA Site Inspector or traffic controller. If anything is unclear or conflicting, stop and call the project access number. |
| X | THE NOTICE BOARD IS NOT PERMISSION TO CROSS Posted access periods and a confirmed request do not authorize entry. Never enter because equipment appears stopped, another resident crossed, or a barrier is open. |
MESSAGES YOU MAY RECEIVE
| STATUS | WHAT IT MEANS |
| ACCEPTED | A proposed crossing time is available. Reply as instructed, arrive at the holding point, and wait for the traffic controller. |
| PENDING | The request is still being coordinated. Do not approach the bridge. Wait for the next update time in the message. |
| DECLINED | The requested time cannot be provided safely. The message will give the reason and, where possible, the next opportunity. |
| CANCELLED / DELAYED | Conditions changed after scheduling. Follow the revised instruction and do not enter the work zone. |
| STOP MEANS STOP If you do not receive a clear signal from the traffic controller, do not proceed. No text message, posted time, wave from an equipment operator, or open barrier replaces the traffic controller’s release. |
EMERGENCY AND REMINDERS
| 911 For fire, police, ambulance, or any immediate threat, call 911 first. Tell dispatch your civic address and that bridge construction may affect access. | NO SELF-ENTRY Never walk or drive into the work area without a clear release and any required escort. |
| EXPECT CHANGE Weather, excavation, equipment movement, or other hazards may delay or cancel a proposed crossing. | KEEP CONTACT CURRENT Tell the project team if your phone number or preferred communication method changes. |
DELIVERIES DURING CONSTRUCTION
Residents are encouraged to have non-essential deliveries, including online orders, sent to an alternative address whenever possible, such as a workplace, family member’s residence, or designated pickup location.
ADDITIONAL CROSSING REQUESTS
Additional crossings outside the scheduled access periods are offered on a best-efforts basis to accommodate higher-priority needs and support residents during construction. Each unplanned crossing requires construction activities to stop and the route to be made safe, which may delay the work and result in additional project costs. To keep this option available, residents are asked to use additional crossing requests only when reasonably necessary. If the process is repeatedly misused, additional crossings may be restricted or discontinued
PROJECT CONTACTS
| CONTACT | INFORMATION |
| Project access requests | (705) 690-7007 | While Contractor is On-Site |
| RVA Site Inspector | Tyler Scott | (705) 690-7007 General Inquiries |
| Municipality project contact | Ronny Theiss | 705-853-4536 ext. 208 publicworks@markstay-warren.ca |
| Emergency | 911 |
KEEP THIS SHEET NEAR YOUR PHONE. CHECK THE NOTICE BOARD BEFORE EACH TRIP.